Construction update project L68 | Bait Al Watan 4 | New Cairo
Construction update project L68 | Bait Al Watan 4 | New Cairo
October 2026 construction update
for Project L68 by Kandeel Developments. Front facade finishing and marble entrance works are underway.
September 2026 construction update.
Facade finishing works are nearing completion.
August 2026 Construction Update
Project L68 | Beit Al Watan District 4
Facade plastering works are underway alongside the completion of internal plastering, advancing the project toward its finishing stage.
July 2026 Construction Update
Project L68 | Beit Al Watan District 4
All masonry works have been completed, and internal plastering works are in their final stages ahead of the next construction phase.
May 2026 Construction Update
Project L68 | Beit Al Watan District 4
All concrete structural works have been successfully completed. Masonry and block works are now actively underway.
April 2026 Update
Project L68 in Bait Al Watan 4, New Cairo — Second floor roof slab works underway. Kandeel Developments continues to deliver on schedule, upholding its commitment to quality and on-time handover.
March 2026 Update
Construction update — project L 68 | Bait Al Watan – 4th District | New Cairo. First floor columns poured. Kandeel Developments is in a race with time to deliver our projects according to the highest quality standards.
February 2026 Update
Ground floor column works are currently in progress at Project L68 – Bait Al Watan 4, in accordance with the scheduled timeline and approved technical specifications.






