Construction update project A 15 | South of Suez Road | New Cairo
Construction update project A 15 | South of Suez Road | New Cairo
April 2026 Update
Project A15 in South Of Suez, New Cairo — Entrance marble finishing in progress. Kandeel Developments continues to deliver on schedule, upholding its commitment to quality and on-time handover.
March 2026 Update
Construction update — project A 15 | South of Suez Road | New Cairo. Entrance marble finishing in progress. Kandeel Developments is in a race with time to deliver our projects according to the highest quality standards.
February 2026 Update
Project A15 has reached the stage of finishing the main entrance. Current operations include the installation of wall cladding and flooring in accordance with the approved engineering blueprints, ensuring full compliance with Kandeel Residence’s technical specifications.
October 2024 Update
A15 project – South of Suez is witnessing continuous progress in construction. Preparations are underway to begin finishing the exterior façades after successfully completing previous stages. On-site teams are currently preparing the façades for finishing works, which will be executed to the highest quality standards in line with the distinctive architectural identity of Kandeel Residence projects.
تحديث اغسطس 2024
-تم الانتهاء من صب القواعد العاديه
-جاري تنفيذ نجاره وحداده القواعد المسلحه
تحديث يوليو 2024
تم الانتهاء من اعمال الحفر حتي منسوب التأسيس .
جاري تجهيز أعمال الغمر والدمك